SR 80 (Southern Blvd) Bridge Replacement Project

Home / Construction Updates

Construction Updates

July 1 to July 30, 2017

Major Activities

  • Drive production pile for temporary bridge
  • Drive sheet pile for temporary wall
  • Remove and relocate light poles

Restrictions: The north sidewalk on the Southern Boulevard Bridge is closed until further notice. Pedestrians should use the south sidewalk.

The eastbound lane of Southern Boulevard between Olive Avenue and Flagler Drive will be closed with eastbound traffic shifted to the north as AT&T performs utility work in the area. One lane of traffic in each direction will be maintained at all times. For more information, please contact Project Manager Dustin Ertle at 561-644-2182